Formulation of an Optimal Production Sequencing Problem in a Complex Free Flow Assembly Line
スポンサーリンク
概要
- 論文の詳細を見る
Instead of conventional constant speed assembly lines, complex free flow assembly lines are sometimes utilized to assemble many product variants in automobile and other industries. In such assembly lines, a job is transferred to the next stage when the transfer is permissible and the next stage is vacant. Two types of buffers, series and parallel, are used along the line. A series buffer can be considered as a stage with a zero processing time. With a parallel buffer, some work can be postponed, i.e., the production sequence can be changed after the parallel buffer. In this paper, we will formulate a production sequencing problem explicitly for a complex free flow assembly line with bypass stages as well as parallel buffers. We validate the formulation by solving some examples using mathematical software. This formulation will be useful to evaluate the objective function value more efficiently than executing a simulation in meta-heuristic algorithms, although the way how to evaluate the objective value using the formulation is not discussed in the paper.
- 社団法人日本経営工学会の論文
- 2008-08-15
著者
-
Dhakar Tej
Department of Quantitative Studies, Operations and Project Management Southern New Hampshire Univers
-
Tamura Takayoshi
Department of Management and Systems Engineering Nagoya Institute of Technology
-
Dhakar Tej
Depart Emt Pf Quantitative Studies Operations And Project Management Southern New Hampshire Universi
-
Dhakar Tej
Department Of Quantitative Studies And Operations Management Southern New Hampshire University
-
Ohno Katsuhisa
Faculty Of Management And Information Science Aichi Institute Of Technology
-
Yamazaki Mototsugu
Research & Development Center, Sekisui Chemical Co., Ltd.
-
Yamazaki Mototsugu
Research & Development Center Sekisui Chemical Co. Ltd.
関連論文
- Establishment of an Efficient Fermentation System of Gamma-Aminobutyric Acid by a Lactic Acid Bacterium, Enterococcus avium G-15, Isolated from Carrot Leaves
- 5B3 DETERMINING REORDER INTERVALS FOR GENERAL PRODUCTION-DISTRIBUTION SYSTEMS
- 4B3 EFFICIENT HEURISTICS FOR DETERMINING NEAR-OPTIMAL LOT SIZES FOR MRP SYSTEMS
- Formulation of an Optimal Production Sequencing Problem in a Complex Free Flow Assembly Line
- A Procedure for a Multi-Item and Multistage Production Planning Problem