5.建築工事の工程管理に関する研究(7) : 予定工程曲線追跡の実際
スポンサーリンク
概要
- 論文の詳細を見る
In the Transactions of A.I.J., No.51, the author has stated the principles of progress control in construction that (1) when the construction work has been delayed, the path which the actual progress curve should follow must be within the cross-hatched area and (2) the tangent of the actual curve should always be kept on the left side of point b after passing point a. In this paper the author states a few remarks on those principles in reference to practical examples. In cases shown below the construction work can kept on punctually, even though the above mentioned two conditions are not satisfied at the same time. Namely, I. When only the condition (1) is satisfied; (A) a case that the tangent of the actual curve is not kept on the left side of point b and also the tangent of the scheduled curve is designed in that way, or (B) a case that the tangent of the actual curve deviates from point b owing to extraordinary progress, II. When only the condition (2) is satisfied; (A) a case that the actual curve is not within the cross-hatched area at the early stage of construction period, or (B) a case that the actual curve is not within the cross-hatched area at the early and middle stage of the period.
- 社団法人日本建築学会の論文
- 1956-03-30
著者
関連論文
- 157 建築工事の工程管理に関する研究(10) : 進度管理を行つた工事の成績(材料・施工)
- 144 建築工事の工程管理に関する研究(9) : 進度管理の実例(材料・施工)
- 22.建築工事の工程管理に関する研究 : 工程曲線と竣工期日との関係(材料・施工)
- 1051 降雨等による休業日数の算定 : 標準工期に関する研究 2(材料・施工)
- 4.建築工事の工程管理に関する研究(8) : 部分工事の予定進度曲線の設計
- 5.建築工事の工程管理に関する研究(7) : 予定工程曲線追跡の実際
- 135 建築工事の工程管理に関する研究 (6) : 出面表の解析とその応用
- 6.建築工事の工程管理に関する研究(5) : 予定工程曲線追跡の方針
- 151 建築工事の工程管理に関する研究 (4) : (予定工程曲線の設計)
- 19. 建築工事の工程管理に関する研究 (3) : (予定工程曲線の畧算法)
- 133. 建築工事の工程管理に関する研究 (2) : 工程曲線の分析