生産準備システム (電算機応用<特集>)
スポンサーリンク
概要
- 論文の詳細を見る
Daido Steel started the system re-build up project for sales, production and distribution of steel bar and wire rod in 1988.Its main purpose was the realization of production control to take a serious view on delivery date priority. A new preparation system of production control was requested for realization of this purpose.The newly built preparation system consists of two sub-systems. One of them is production design system. It was re-built in system suitable for new production control. Another of them is order entry control system. It was newly developed for automatic checking of the required delivery date of each order.The preparation system was completed in 1991 and the system operation started. Now, among the orders entried to Chita Plant, 90% of which are completed production design within the entry day, and the checking results of the required delivery date are available on each terminal of sales and production departments on the next day.