シンガポール地下鉄プロジェクトに関する報告(<特集>インフラ海外展開における地盤分野の取組み)
スポンサーリンク
概要
- 論文の詳細を見る
In Singapore which has a land area of approximately 710km^2, total 4 numbers of MRT line currently open for revenue service. In 2020, total 278 km long line will open inclusive Downtown Line (under construction), Thomson Line and Eastern Region Line (under design). Singapore has a small land area, but the ground condition often changes abruptly from stable to unstable due to the presence of faults and valley structures even in localized areas. Through many experiences of MRT project, some major troubles had occurred due to such ground conditions. In this report, the summary of Contract C929A in Downtown Line project is indicated and current mitigation measures as risk management are elaborated based on our past experiences in Singapore.
- 2012-09-01