2A3 DEVELOPMENT OF A SHIPBUILDING SCHEDULING SYSTEM UTILIZING A WEIGHTED CONSTRAINT SATISFACTION PROBLEM SOLVER(Technical session 2A: Application and practice 1)
スポンサーリンク
概要
- 論文の詳細を見る
The streamlining of the construction process is an imminent problem in the shipbuilding industry. To that end, some companies have started to introduce production optimizing approach like Toyota Production System. However, as for the production scheduling, the dependency level on the undocumented human experiences remains still very high. It has been due to the difficulties stemming from the complexity of human decision processes. In this paper, we propose to formulate the concerned problem with Weighted Constraint Satisfaction Problem approach. With the approach especially adapted to the bottleneck processes, we have confirmed the improvement of the existing scheduling processes.
- 一般社団法人日本機械学会の論文
- 2006-07-18
著者
-
Nishimura Takuya
Sumitomo Heavy Industries Ltd.
-
Makino Yuki
Sumitomo Heavy Industries Marine Engineering Ltd.
-
Nakama Yukihiro
Sumitomo Heavy Industries, Ltd.
-
Matsuda Masayasu
Sumitomo Heavy Industries Marine Engineering, Ltd.
-
Nakama Yukihiro
Sumitomo Heavy Industries Ltd.
-
Matsuda Masayasu
Sumitomo Heavy Industries Marine Engineering Ltd.
-
Matsuda Masayasu
Sumitomo Heavy Industries Ltd.
関連論文
- 2A3 DEVELOPMENT OF A SHIPBUILDING SCHEDULING SYSTEM UTILIZING A WEIGHTED CONSTRAINT SATISFACTION PROBLEM SOLVER(Technical session 2A: Application and practice 1)
- Dynamic Characteristics of a Gyroscope and a Vibration Absorber
- Studies on Nonlinear Torsional Vibration of Marine Steam Turbine Propulsion Shafting