MCFC Research Association has made research and development of MCFC for the National project since 1988. We made operation of 1000kW class pilot plant in 1999,and recently high pressure operation with 10kW stack was achieved 1.2MPa operation for combined cycle. We have new program of MCFC power system, 300kW class for commercialization. It has been operated from this year with alternative air supplying system in place of turbo charger generator, and has suggested the good performance and good efficiency. In this paper, we introduce the schedule and the results of the system.